BELOYARSK NPP: On site assistance.

 
BELOYARSK NPP: On site assistance.

Description

Objective

According to the intention of the European Union and the Russian Ministry of Atomic Power the operational safety assistance, which started with TACIS 92 continued with TACIS 98 with the same Western and Eastern Utility and NPPs. Similar to the procedure in TACIS 92 a joint Western/Eastern working team was to be set up to continue the work started in TACIS 92.

In the present case EDF is the Consultant, contracted by EC to provide operational safety assistance to Beloyarsk NPP.

Result

The projects, defined under the Tacis budget 1998 have been supported by the Western Utility in the following aspects:

Setting up of a Technical Specification (TS);
Agreement with EC and Beneficiary on the TS;
Assistance in the procurement process;
Assistance in custom clearance;
Assistance in installation of the equipment.
Further general assistance has been given by the Western Utility in upgrading the safety culture on the NPP.


General Information

Title: 
BELOYARSK NPP: On site assistance.
Programme: 
TACIS
Amount: 
€ 700.000,00
Budget year: 
1998
Countries: 
Russia
Nature: 
Services
Types of activities: 
On Site Assistance
NPP: 
Beloyarsk
Duration (months): 
22
Contracting authority: 
European Commission
Partner (Beneficiary): 
Rosenergoatom
Contractors: 
EDF (Electricite de France)
Status: 
Closed
CRIS number: 
26576
Old reference: 
00-0304
Project reference: 
R1.06/98
Decision number: 
TACIS/1998/000-477
Method of procurement: 
Direct Agreement
Signature date: 
22/02/2001
Effective contract date: 
22/02/2001
Contract end date: 
22/12/2002
Closure date: 
03/06/2005