Objective
With this project, the modernization of the Emergency Power Supply System (EPSS) has been started in the framework of the Tacis programme. The supply consisted of four 400 V, 3-phase, 3-wire, 50 Hz Switchgears with the relevant accessories and spare parts as well as 70 emergency circuit breakers as listed in the attached Table 1 (excerpt from the Technical Specification), Parts 1 and 2 (Lots 1.1 and 1.2).� It was also intended to purchase a new telephone exchange system for the power plant (attached table, Part 3 [Lot 2]), but this was cancelled from the scope of supply following unsuccessful call for tender for this lot.
Remark:
In supplement to this project R1.08/95, project R1.02/97D has been set up.
Result
The project has been contracted on 11.3.2004 and has been completed, except part 3.