Continuation of the Implementation of some backlog-projects of Tacis 94-95-96-97 programme for Balakovo

 
Continuation of the Implementation of some backlog-projects of Tacis 94-95-96-97 programme for Balakovo

Description

Background

Due to a backlog of several Tacis equipment supply projects for Balakovo NPP, caused by external factors, there was an urgent need to make provisions for the proper follow-up of these projects.

In order to cater for this, an additional contract was placed with the then current OSA Consultant at Balakovo NPP.

Objectives

The specific objective of this contract was to continue the implementation of the following backlog projects of the TACIS 94, 95, 96 and 97 programmes for the Balakovo NPP: R1.02/94E, R1.02/95B, R1.02/96B, R1.02/96C/97A, R1.02/96D, R1.02/97C.

The work to be performed for these specific projects was as follows:

  • R1.02/94E: SG Safety Valves: Target: installation, commissioning and provisional acceptance of the safety valves in the unit 4 outage (June-July 2003).
  • R1.02/95B: BRU-A: Target: Approval of design documentation, completion of the manufacturing and the head sample tests.
  • R1.02/96B: Pilot Valves for Pressurizer Safety Valves: Target: Completion of the manufacturing, the head sample tests and the workshop acceptance.
  • R1.02/96C/97A: ECCS Sump Filter System: Target: Completion of the tendering and contracting phase as well as initial phase of the supply project (kick-off meeting).
  • R1.02/96D: Fuel Loading Machine I and C: Target: Completion of the contracting phase as well as the initial phase of the supply project (kick-off meeting).
  • R1.02/97C: Leakage Monitoring System: Target: endorsement of technical specifications, tendering and contracting phases.

Results

The contract was signed on 4 July 2003 and was completed by 4 January 2005.

Only the objectives related to R1.02/97C were not achieved. The Technical Specification was prepared and endorsed but the call for tender was not launched because the project was cancelled and re-programmed in the Tacis AP2003 (Project R1.02/03A). It was later successfully contracted.


General Information

Title: 
Continuation of the Implementation of some backlog-projects of Tacis 94-95-96-97 programme for Balakovo
Programme: 
TACIS
Amount: 
€ 139.879,98
Budget year: 
2001
Countries: 
Russia
Nature: 
Services
Types of activities: 
On Site Assistance
NPP: 
Balakovo
Duration (months): 
18
Contracting authority: 
European Commission
Contractors: 
RRCKI ( Russian Research Centre Kurchatov Institute)
Status: 
Closed
CRIS number: 
61027
Decision number: 
TACIS/2001/000-558
Method of procurement: 
Direct Agreement
Signature date: 
04/07/2003
Effective contract date: 
04/07/2003
Contract end date: 
04/01/2005
Closure date: 