Description

Beneficiary Organizations Details

 
Nuclear Installations Decommissioning, Radwaste and Spent Fuel Management Company:

http://www.seas.sk
 

 
Project Aims

 
 
The overall objective of this project was to facilitate decommissiong of the nuclear power plant A-1 (HWGCR) in Slovak Republic. The specific objective was to prepare supporting documentation required for development and realization of the Second Phase of NPP A-1 decommissioning.
 

Project Results

 
 

  1. System (technical and conceptual solution) for internal diagnostics of KS-150 reactor and entire primary circuit.
  2. Technical and conceptual solution for separation of KS-150 reactor vesel from the primary circuit loops and pipelines.
  3. Technical and conceptual solution for draining off remaining D2O from lower parts of the KS-150 reactor vesel.
  4. Proposal of a a system for monitoring of state of KS-150 reactor during the phase of its protective enclosure.
  5. Conceptual design of decontamination procedures for technological equipment of NPP A-1 primary circuit, and
  6. Definition of initial conditions, priorities, possible decontamination technologies, decontamination reagents, etc..

 
The budget for this project was: 1 250 000 euro.
 
Further Project Results
 
Further information on the project could be sought from the beneficiary organizations.


General Information

Title: 
Decontamination of NPP A-1 Primary Circuit
Programme: 
PHARE
Budget year: 
2002
Countries: 
Slovakia
NPP: 
Bohunice
Duration (months): 
150
Status: 
On-going
Old reference: 
632.09.01
Effective contract date: 
01/01/2003
Closure date: 
30/09/2005