Establishment of industrial facility for removal of trans-uranium elements and organics from process water and liquid radioactive waste at ChNPP - Phase I

 
Establishment of industrial facility for removal of trans-uranium elements and organics from process water and liquid radioactive waste at ChNPP - Phase I

Description

The project summary will be published after the completion of the project.
The purposes of this contract are as follows:
·    a   design   documentation   of   the   industrial   purification   facility   including   the environmental impact assessment and safety assessment documentation,
·    detailed technical specification, tender dossier and cost assessment for the project for the supply of the industrial purification facility,
·    a monitoring of the implementation of the industrial purification facility supply project, including supervision of its installation, setting-up, testing and commissioning,
·    a complete set of engineering documentation for the industrial purification facility and a final safety assessment report.


General Information

Title: 
Establishment of industrial facility for removal of trans-uranium elements and organics from process water and liquid radioactive waste at ChNPP - Phase I
Programme: 
INSC
Amount: 
€ 1.659.008,50
Budget year: 
2011
Meta geographical zone: 
Chernobyl
Countries: 
Ukraine
Nature: 
Services
Types of activities: 
Waste Management
Sector: 
WDS - Waste, Decommissioning and Safeguards
NPP: 
Chernobyl
Duration (months): 
35
Partner (Beneficiary): 
Government of Ukraine
Contractors: 
Nukem
Status: 
Closed
CRIS number: 
348291
Project reference: 
U4.01/11
Decision number: 
NSI/2011/023-466
Method of procurement: 
Service contracts - International Restricted Procedure with prior publication
Signature date: 
22/08/2014
Effective contract date: 
01/09/2014
Contract end date: 
31/05/2017
Closure date: 
05/03/2020