FOLLOW-UP OF CONTRACT R2.12/94 MFS ADAPTATION TO NOVOVORONEZH TRAINING CENTER NEEDS

 
FOLLOW-UP OF CONTRACT R2.12/94 MFS ADAPTATION TO NOVOVORONEZH TRAINING CENTER NEEDS

Description

Objective
The wider objective of the project was intended to strengthen the Nuclear Safety through the support of the training system and training facilities at Russian NPP’s.
The main specific objective was to implement the connection of the existing multifunctional simulator to control panels at the Novovoronezh Training Centre by supplying a modern state-of-the-art full scope replica simulator for training of operators of the Novovoronezh unit and other similar units in Russia and other countries, thus providing a direct contribution to the improvements of operational safety of older generation VVER-440 NPPs in Russia. The simulator had to represent the real control room of Novovoronezh Unit 3. This work required a certain amount of modifications within the original simulation system, the installation, connection, and testing of an Input/Output system for the communication between the simulation computer and the control panels. It was not expected to implement any model adaptations or modifications, which may have been required due to the evolution of the reference plant since the delivery of the multifunctional simulator. The contract also included the activities necessary to complete the the work started under contract 24692.
The detailed description of the work performed by the Consultant is presented below:
Task 1: Project preparation
-verification of the existing data package and specification,
-preparation of remaining open questions,
-preparation of detailed project programme and organisation,
-preparation of detailed project time schedule and the project related Q-A-programme.
Task 2:On-site start-up workshop
-discussion of the detailed project programme and organisation,
-discussion of detailed project time schedule,
-I/O acceptance tests specification
-examination of the remaining open questions – final agreement on scope definition in conformity with the ToR.
Task 3: Connection methodology and I/O system design
-I/O system implementation design,
-I/O system cabling design and instructions.
Task 4: On-site training
-cabling methodology,
-software tools for MFS software adaptation.
Task 5: I/O system delivery and cabling
-I/O system purchase,
-I/O system verification,
-I/O system transportation,
-I/O cabling
Task 6: MFS software adaptation
-adaptation of the existing software to the new operational environment,
-development of communication software.
Task 7: On-site integration
-implementation of the modified software,
-implementation of the communication software,
-new instructor station functionality.
Task 8: Validation
-communication system validation,
-know-how transfer on maintenance procedures to the maintenance staff of the beneficiary by means of a hands-on workshop.
Project Results
The project was completed according to the Terms of Reference requests.
The following items were delivered in the course of the project:
Task 1 and 2
Deliverable 1:
-detailed project schedule,
-project Q-A Plan,
-configuration management procedure
Task 3, 4 and 5
Deliverable 2:
-hard panels cabling methodology guideline,
-design file for I/O system implementation,
-guideline for the I/O cross reference database,
-I/O system testing methodology.
Task 6 and 7
Deliverable 3:
-specification file for Instructor station upgrades,
-specification and design files for the communication software,
-software integration plan,
-result of the unit testing for the communication software,
-user and maintenance manuals.
Task 8
Deliverable 4:
-acceptance tests reports filled in,
-taking over certificate signed.


General Information

Title: 
FOLLOW-UP OF CONTRACT R2.12/94 MFS ADAPTATION TO NOVOVORONEZH TRAINING CENTER NEEDS
Programme: 
TACIS
Amount: 
€ 450.000,00
Budget year: 
1998
Countries: 
Russia
Nature: 
Services
Sector: 
DS - Design safety (incl. Off-Site Emergency Preparedness)
NPP: 
Novovoronezh
Duration (months): 
12
Contracting authority: 
European Commission
Contractors: 
CORYS T.E.S.S.
Status: 
Closed
CRIS number: 
30372
Decision number: 
TACIS/1998/000-477
Method of procurement: 
Direct Agreement
Signature date: 
02/09/2002
Effective contract date: 
02/09/2002
Contract end date: 
02/09/2003
Closure date: 
04/06/2007