Navigation path

Improvement of the I & C System Neutron Flux Source Range Monitoring System - Medzamor NPP - Armenia

 
Improvement of the I & C System Neutron Flux Source Range Monitoring System - Medzamor NPP - Armenia

Description

Objective

The project objective was to replace the obsolete neutron flux monitoring system in the source ran ge. This was the safety issue identified in the IAEA issue book. By implementing this project, the plant safety has been substantially improved. The control room operators have a credible and reliable information needed during the reactor start up as well as reactor shut down.

Results

The kick-off meeting was held on-site on Feb 10th, 2004. The Supplier presented a revised project schedule, accepted by the plant, with delivery not earlier than December 2004 (outside 2004 outage timeframe). A new updated project schedule, approved by ANPP, considered installation of equipment during the October 2005 outage, with delivery in April-May 2005.

Factory acceptance tests were successfully performed in April 2005. An Audit related to the S/W validation process was performed by RiskAudit at supplier premises at the end of May 2005. The audit included also PRZ SV COP S/W validation as remaining open issue of the TACIS 96 Programme. The S/W validation process set by the supplier was considered satisfactory, closing then this long licensing issue.

The equipment was delivered to the site on May 31st, 2005; commissioning test procedure was issued at the end of July. Preliminary installation activities for equipment installation (e.g. system cabling) were performed during the last outage, while final cabinet installation and system installation is planned during 2006 outage. The Provisional Acceptance certificate (partial PA for services) was signed the 25th of January 2006.


General Information

Title: 
Improvement of the I & C System Neutron Flux Source Range Monitoring System - Medzamor NPP - Armenia
Programme: 
TACIS
Amount: 
€ 1.300.000,00
Budget year: 
2000
Countries: 
Armenia
Nature: 
Supply
Types of activities: 
Equipment Supply
NPP: 
Medzamor
Duration (months): 
17
Contracting authority: 
Armenian Nuclear Power Plant
Partner (Beneficiary): 
Armenian Nuclear Power Plant
Contractors: 
Data Systems & Solutions
Status: 
Closed
CRIS number: 
30574
Project reference: 
A1.01/00 B3
Decision number: 
TACIS/2000/000-538
Method of procurement: 
Open Call for Tender
Signature date: 
23/12/2003
Effective contract date: 
23/12/2003
Contract end date: 
23/05/2005
Closure date: 
22/04/2008