Improvement of I & C system - Primary and secondary water chemistry

 
Improvement of I & C system - Primary and secondary water chemistry

Description

Objective

This project aimed at improving instrumentation needed for monitoring of the plant chemistry parameters. The scope of supply included Instrument cabinets; Electric boxes; Piping for sampling and drains; Set of material for piping fitting; Calibration, testing and maintenance tools set, Computer system ; Printer; Network equipment, Network cables; Full software package and licence; Shop acceptance test; Supervision to installation and site acceptance tests; Operation and maintenance training; Licensing assistance, Set of spare parts for installation, fitting and commissioning and warranty period.

Results

A survey on similar previous projects developed in the framework of Tacis and Phare programmes has been performed and the existing system at ANPP has been carefully reviewed in order to finalize the necessary improvements. The first draft of Technical Specification has been prepared by Sogin and sent to ANPP.

A meeting, necessary to complete the Technical Specification was held in April 2000 at ANPP. Some information necessary to complete the Technical Specification has been requested to ANPP. A second draft of the Technical Specification was sent to ANRA on May 2002. Comments by ANRA/Riskaudit have been discussed during the licensing meeting of the 12-13 June onsite and the applicable ones have been included in the revised Technical Specification.

The contract forecast was sent to the EC for publication on EC web site on July 26th, 2002. The final version of Technical Specification and Evaluation Criteria was approved by JRC on Dec. 19th, 2002.

Factory Acceptance Tests were performed on September 2004. On February 2005 the Contracting Authority and the Supplier agreed on a new delivery schedule An addendum for contract regularisation, endorsed by EC on April 14th, 2005, was signed by ANPP (May 25th).Installation of the equipment has been completed (September 2005) and provisional acceptance was issued on the 2nd of September.


General Information

Title: 
Improvement of I & C system - Primary and secondary water chemistry
Programme: 
TACIS
Amount: 
€ 988.077,63
Budget year: 
2000
Countries: 
Armenia
Nature: 
Supply
Types of activities: 
Equipment Supply
NPP: 
Medzamor
Duration (months): 
14
Contracting authority: 
Armenian Nuclear Power Plant
Partner (Beneficiary): 
Armenian Nuclear Power Plant
Contractors: 
All Trade Italy
Status: 
Closed
CRIS number: 
72771
Project reference: 
A1.01/00B5
Decision number: 
TACIS/2000/000-538
Method of procurement: 
Open Call for Tender
Signature date: 
23/12/2003
Effective contract date: 
23/12/2003
Contract end date: 
23/02/2005
Closure date: 
02/04/2008