This project aimed at replacing the obsolete radiological Instrumentation and increase capability of the plant radiation monitoring system.
Result
A progress meeting was held on-site on October 7th, 2004 and a final schedule with a new delivery time of 16 months (April 2005) was agreed upon. Addendum 1 to Contract n. 2003/072-768, including new delivery deadline, was endorsed by EC on February 17th, 2005.
Factory acceptance tests were successfully performed in June 2005 and equipment was delivered on-site. Installation activities were completed during the 2005 outage.
General Information
Title:
Improvement of I & C Systems - Modernisation of Radiation Monitoring System
Programme:
TACIS
Amount:
€ 959.180,00
Budget year:
2000
Countries:
Armenia
Nature:
Supply
Types of activities:
Equipment Supply
NPP:
Medzamor
Duration (months):
16
Contracting authority:
Armenian Nuclear Power Plant
Partner (Beneficiary):
Armenian Nuclear Power Plant
Contractors:
Canberra
Status:
Closed
CRIS number:
72768
Project reference:
A1.01/00B4
Decision number:
TACIS/2000/000-538
Method of procurement:
Negotiated Procedure
Signature date:
22/12/2003
Effective contract date:
22/12/2003
Contract end date:
22/04/2005
Closure date:
23/05/2008