Improvement of I & C Systems - Modernisation of Radiation Monitoring System

 
Improvement of I & C Systems - Modernisation of Radiation Monitoring System

Description

Objective

This project aimed at replacing the obsolete radiological Instrumentation and increase capability of the plant radiation monitoring system.

Result

A progress meeting was held on-site on October 7th, 2004 and a final schedule with a new delivery time of 16 months (April 2005) was agreed upon. Addendum 1 to Contract n. 2003/072-768, including new delivery deadline, was endorsed by EC on February 17th, 2005.

Factory acceptance tests were successfully performed in June 2005 and equipment was delivered on-site. Installation activities were completed during the 2005 outage.


General Information

Title: 
Improvement of I & C Systems - Modernisation of Radiation Monitoring System
Programme: 
TACIS
Amount: 
€ 959.180,00
Budget year: 
2000
Countries: 
Armenia
Nature: 
Supply
Types of activities: 
Equipment Supply
NPP: 
Medzamor
Duration (months): 
16
Contracting authority: 
Armenian Nuclear Power Plant
Partner (Beneficiary): 
Armenian Nuclear Power Plant
Contractors: 
Canberra
Status: 
Closed
CRIS number: 
72768
Project reference: 
A1.01/00B4
Decision number: 
TACIS/2000/000-538
Method of procurement: 
Negotiated Procedure
Signature date: 
22/12/2003
Effective contract date: 
22/12/2003
Contract end date: 
22/04/2005
Closure date: 
23/05/2008