Improvement of the infrastructure for radioactive waste management in the Chernobyl Exclusion Zone. Phase I: Safety assessment

 
Improvement of the infrastructure for radioactive waste management in the Chernobyl Exclusion Zone. Phase I: Safety assessment

Description

The project summary will be published after the completion of the project. The project consists of a service contract (Phase I) and a works contract that includes equipment procurement (Phase II) which may or may not go forward (in part or in whole) depending on the outcome of the service contract. This ToR is concerned only with the service contract. Objectives of the service contract: • To develop concept projects whose contents meet the Technical and Economic Calculations (TEC) (see DBN А.2.2-3 2004) for the mobile roof for trenches and the entry control station. • To assess the operational and post-closure safety of the object in its current state (work to be presented in a Safety Analysis Report (SAR) for «Buryakovka») and in the planned renovated state, taking into account the modified design and the expected volume of future waste deliveries (through a preliminary SAR considering the facility as if the modified design and increased capacity were approved). • To develop recommendations on waste characterization methods and equipment for showing compliance of waste with acceptance criteria. To prepare technical specifications for the recommended equipment. • To prepare detailed terms of reference/technical specifications for the renovation and expansion of RWBF «Buryakovka», required for the works envisaged under Phase II. Depending of the results of the service contract (Phase I), Phase II of the project (renovation of RWBF «Buryakovka») may be implemented in part or in its entirety: • Development of detailed designs for the mobile roof for trenches and the entry control station. • Development of the working plan on the basis of design decisions and preliminary SAR. • Purchase and supply of equipment and expendable materials for the analytic laboratory of SSSIE «Ecocenter» and the entry control station of RWBF «Buryakovka». • Construction and commissioning of the renovated project. • Preparation of the final safety analysis report.


General Information

Title: 
Improvement of the infrastructure for radioactive waste management in the Chernobyl Exclusion Zone. Phase I: Safety assessment
Programme: 
INSC
Amount: 
€ 487.001,30
Budget year: 
2008
Countries: 
Ukraine
Nature: 
Services
Types of activities: 
Waste Management
Sector: 
WDS - Waste, Decommissioning and Safeguards
NPP: 
Chernobyl
Installation types: 
RBMK
Duration (months): 
16
Contracting authority: 
European Commission
Contractors: 
DBE Technology
Status: 
Closed
CRIS number: 
230580
Project reference: 
U4.01/08B
Decision number: 
NSI/2008/020-363
Method of procurement: 
Restricted Call for Tender
Signature date: 
22/10/2010
Effective contract date: 
22/11/2010
Contract end date: 
21/05/2014
Closure date: 
10/11/2015