Navigation path

MULTIFUNCTIONAL COMPACT SIMULATOR NOVOVORONEZH

 
MULTIFUNCTIONAL COMPACT SIMULATOR NOVOVORONEZH

Description

Objective / Tasks

The project is a small part of a general project aimed to develop and deliver simulation tools to be installed on the VVER-440-NPP sites (230/213). Multifunctional Simulators (MFS) had to be supplied and delivered to Novoronezh Training Centre and Kola NPP (See project R2.04/93).

At Kola, one multifunctional graphical interface simulator was to be installed with the capabilities to run two models (one 230 and one 213). For Novovoronezh, the project had to be in line with the results of the feasibility study and the data collection performed under TACIS 91 (project 1.7).

In the frame of the future project dedicated to the supply of Multifunctional simulators (R2.04/93), it was necessary to perform additional tasks to what had been included in the initial scope of TACIS 91/1.7.

These tasks were:
- presentation to and appraisal by the representatives of the other project parties of the methodology designed to collect and organise the data of the Novovoronezh reference plant;
- collection of the additional data specific to the other target 440/230 units.

This data collection had to be organised in total conformity with the work performed for Novovoronezh reference plant.
This additional work was performed under a separate contract with the main contractor of the Tacis 91/1.7 project.

Project Results

The parties involved were:
- Belgatom as project leader of the 1.7 Project,
- Atomtechenergo and the Novovoronezh training centre Organisation.
- Nuclear power plant management or local organisations representing them of the other recipient countries.
- Commission of the European Union as contracting party.

The technical documentation related to the collection of the Novovoronezh nuclear power plant data was made available through the 1.7 Project.

A meeting was organized during which the structure of this documentation was described and a procedure to analyse and structure the differences between plants was set up.

The other parties involved then had to work out documents to serve as a basis to develop the proper data package of their own plants.

The resulting documentation served as a basis for the future contract (R2.04/93) that would be launched for the construction of Multifunctional simulators.

The results of this work were available in September 1994.


General Information

Title: 
MULTIFUNCTIONAL COMPACT SIMULATOR NOVOVORONEZH
Programme: 
TACIS
Amount: 
€ 19.904,00
Budget year: 
1993
Countries: 
Russia
Nature: 
Services
Types of activities: 
Design safety
Sector: 
DS - Design safety (incl. Off-Site Emergency Preparedness)
Duration (months): 
2
Contracting authority: 
European Commission
Contractors: 
Belgatom
Status: 
Closed
CRIS number: 
22686
Old reference: 
94-0600
Decision number: 
TACIS/1993/000-363
Method of procurement: 
Direct Agreement
Signature date: 
25/07/1994
Effective contract date: 
25/07/1994
Contract end date: 
25/09/1994
Closure date: 
25/09/1994