Navigation path

Remediation of the area surrounding the tailings pond at Kowary

 
Remediation of the area surrounding the tailings pond at Kowary

Description

Beneficiary Organisation Details

Technical University:
StanislawStaszicUniversity of Mining and Metallurgy in
Cracow
.
www.agh.edu.pl

Project Aims

The main objective of the project was to provide assistance in establishment of assessment capabilities needed to address the safety issues related to the remediation of the contaminated area surrounding the uranium mining tailings pond at Kowary.

Project Results

The project proceeded in accordance with the Terms of Reference.

The budget for this project was 89 000 euro.

Further Project Results

Further information on the project results could be sought from the beneficiary organisations.


General Information

Title: 
Remediation of the area surrounding the tailings pond at Kowary
Programme: 
PHARE
Budget year: 
1998
Countries: 
Poland
Types of activities: 
Waste Management
Installation types: 
Radioactive Waste
Duration (months): 
150
Contractors: 
G.E.O.S. Ingenieurgesellschaft
Sub-contractors: 
-0
Status: 
Completed
Old reference: 
050-759
Effective contract date: 
01/01/2003
Closure date: 
01/10/2003