Rovno NPP - Solid Radioactive Waste Treatment Facility; Lot 4: Activity Measurement

 
Rovno NPP - Solid Radioactive Waste Treatment Facility; Lot 4: Activity Measurement

Description

This contract is for the the design, manufacture, delivery, etc. including supervision of installation etc of Radiation and Contamination Monitoring Equipment:
-
aerosol activity stationary monitor
-
radiation dose rate mobile monitor
-
radiation dose rate stationary monitor
-
personnel surface contamination mobile monitor
- set of components, accessories and tools (if needed) for installation and maintenance for each type of monitors listed above
- set of components, accessories and tools for calibration (including reference radioactive sources for calibration) for each type of monitors listed above
to
Rivne Nuclear Power Plant, Ukraine


General Information

Title: 
Rovno NPP - Solid Radioactive Waste Treatment Facility; Lot 4: Activity Measurement
Programme: 
TACIS
Amount: 
€ 576.380,00
Budget year: 
2006
Countries: 
Ukraine
Nature: 
Supply
Types of activities: 
On Site Assistance
NPP: 
Rovno
Duration (months): 
45
Contracting authority: 
Energoatom
Partner (Beneficiary): 
EnergoAtom
Contractors: 
ENVINET
Status: 
Closed
CRIS number: 
132884
Project reference: 
U1.01/06
Decision number: 
TACIS/2006/018-041
Method of procurement: 
Open Call for Tender
Signature date: 
03/04/2008
Effective contract date: 
03/07/2008
Contract end date: 
03/04/2012
Closure date: 
19/02/2014