Severe Accident Management Guidelines for Angra 2 NPP, Brazil
Severe Accident Management Guidelines for Angra 2 NPP, Brazil
Description
The project summary will be published after the completion of the project.
The project purpose is to reach a situation in which:
- Eletronuclear has established an improved strategy for beyond design basis and severe accident management for Angra 2 during at power conditions
- Eletronuclear will be able to further develop and maintain Severe Accident Management Strategies and Guidelines for Angra 2 in accordance with international practice
- Eletronuclear staff will be trained in developing and implementing the new guidelines with respect to Eletronuclear practices related to safe operation of nuclear power plants.
General Information
Title:
Severe Accident Management Guidelines for Angra 2 NPP, Brazil
Programme:
INSC
Amount:
€ 1.427.311,74
Budget year:
2009
Countries:
Brazil
Nature:
Services
Types of activities:
On Site Assistance
Duration (months):
35
Contracting authority:
European Commission
Contractors:
Areva
Status:
Closed
CRIS number:
262329
Project reference:
BR1.01/09 T1
Decision number:
NSI/2009/021-880
Method of procurement:
Restricted Call for Tender
Signature date:
09/03/2011
Effective contract date:
22/03/2011
Contract end date:
21/06/2015
Closure date:
02/12/2015