Background
The accident at the Chernobyl Nuclear Power Plant in Ukraine in April 1986 demonstrated the need for adequate radiation early warning systems that allow authorities to take appropriate and timely actions in the event of a major radiological accident.
Search
5 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
- (-) Remove Closed filter Closed (5)
Contract information field: Contractor
Contract information field: Sector
- (-) Remove DS - Design safety (incl. Off-Site Emergency Preparedness) filter DS - Design safety (incl. Off-Site Emergency Preparedness) (5)
Contract information field: Types of activities
- (-) Remove Emergency Preparedness filter Emergency Preparedness (5)
- Design safety (45) Apply Design safety filter
- Training (10) Apply Training filter
- Equipment Supply (3) Apply Equipment Supply filter
- RBMK studies (3) Apply RBMK studies filter
- Studies (3) Apply Studies filter
- Probabilistic Safety Analysis (2) Apply Probabilistic Safety Analysis filter
Contract information field: Partner (Beneficiary)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Belarus, Ukraine
Programme:
TACIS
Budget year:
1991
Amount:
€ 298.846,00
Countries:
Ukraine
Programme:
TACIS
Budget year:
1991
Amount:
€ 272.923,04
Project Description
Countries:
Belarus, Lithuania, Russia, Ukraine
Programme:
TACIS
Budget year:
1991
Amount:
€ 264.453,43
Background
The accident at the Chernobyl Nuclear Power Plant in Ukraine in April 1986 demonstrated the need for adequate radiation early warning systems that allow authorities to take appropriate and timely actions in the event of a major radiological accident.
Countries:
European Union
Programme:
TACIS
Budget year:
1994
Amount:
€ 53.032,00
Background
Countries:
Armenia, Belarus, Georgia, Jordan, Ukraine
Programme:
INSC
Budget year:
2008
Amount:
€ 817.000,00
Background