Background
Search
4 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- 2006 (1) Apply 2006 filter
- 2005 (1) Apply 2005 filter
- 2004 (1) Apply 2004 filter
- 2003 (18) Apply 2003 filter
- 2002 (15) Apply 2002 filter
- 2001 (5) Apply 2001 filter
- 2000 (15) Apply 2000 filter
- (-) Remove 1999 filter 1999 (4)
- 1998 (6) Apply 1998 filter
- 1997 (39) Apply 1997 filter
- 1996 (78) Apply 1996 filter
- 1995 (69) Apply 1995 filter
- 1994 (86) Apply 1994 filter
- 1993 (27) Apply 1993 filter
- 1992 (58) Apply 1992 filter
Contract information field: Status
Contract information field: Contractor
Contract information field: Sector
Contract information field: Types of activities
- (-) Remove Training filter Training (3)
- (-) Remove Equipment Supply filter Equipment Supply (1)
- (-) Remove Safeguards filter Safeguards (0)
- Technical Support Organisations (6) Apply Technical Support Organisations filter
- On Site Assistance (5) Apply On Site Assistance filter
- Waste Management (3) Apply Waste Management filter
- Design safety (2) Apply Design safety filter
- Mitigation of Chernobyl accident (2) Apply Mitigation of Chernobyl accident filter
- RBMK studies (2) Apply RBMK studies filter
- Studies (1) Apply Studies filter
- Technical expertise (1) Apply Technical expertise filter
Contract information field: Partner (Beneficiary)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 59.662,00
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 59.392,00
Project Aims
This project main objective was the improvement of the operational safety of Russian VVER NPPs through the increase of the expertise level of specialists for non-destructive testing.
The specific objectives were:
Countries:
Armenia, Russia, Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 488.001,98
Objective
With this project Training of NPP Operators at CAG Greifswald full scale simulator was planned.
(2 weeks courses for 6-7 participants were foreseen)
Result
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 46.274,71
Background