Project Aims
Search
8 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- 2012 (2) Apply 2012 filter
- 2011 (2) Apply 2011 filter
- 2010 (6) Apply 2010 filter
- 2009 (13) Apply 2009 filter
- 2008 (4) Apply 2008 filter
- 2007 (8) Apply 2007 filter
- 2006 (12) Apply 2006 filter
- 2005 (5) Apply 2005 filter
- 2004 (18) Apply 2004 filter
- 2003 (7) Apply 2003 filter
- 2002 (6) Apply 2002 filter
- 2001 (10) Apply 2001 filter
- 2000 (10) Apply 2000 filter
- (-) Remove 1999 filter 1999 (8)
- 1998 (11) Apply 1998 filter
- 1997 (19) Apply 1997 filter
- 1996 (22) Apply 1996 filter
- 1995 (25) Apply 1995 filter
- 1994 (23) Apply 1994 filter
- 1993 (16) Apply 1993 filter
- 1992 (42) Apply 1992 filter
- 1991 (40) Apply 1991 filter
Contract information field: Status
Contract information field: Contractor
- Dtn (Desarrollo Tecnologico Nuclear) (2) Apply Dtn (Desarrollo Tecnologico Nuclear) filter
- DECOM (1) Apply DECOM filter
- Elektrogorsk Research and Engineering Center on NPP Safety (1) Apply Elektrogorsk Research and Engineering Center on NPP Safety filter
- GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) (1) Apply GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) filter
- Italtrend (1) Apply Italtrend filter
- RRCKI ( Russian Research Centre Kurchatov Institute) (1) Apply RRCKI ( Russian Research Centre Kurchatov Institute) filter
- TVONS (TVO Nuclear Services Oy) (1) Apply TVONS (TVO Nuclear Services Oy) filter
Contract information field: Sector
Contract information field: Types of activities
- (-) Remove On Site Assistance filter On Site Assistance (5)
- (-) Remove RBMK studies filter RBMK studies (2)
- (-) Remove Studies filter Studies (1)
- Regulatory Authorities (7) Apply Regulatory Authorities filter
- Technical Support Organisations (7) Apply Technical Support Organisations filter
- Waste Management (4) Apply Waste Management filter
- Training (3) Apply Training filter
- Design safety (2) Apply Design safety filter
- Mitigation of Chernobyl accident (2) Apply Mitigation of Chernobyl accident filter
- Emergency Preparedness (1) Apply Emergency Preparedness filter
- Equipment Supply (1) Apply Equipment Supply filter
- Safeguards (1) Apply Safeguards filter
- Technical expertise (1) Apply Technical expertise filter
Contract information field: Partner (Beneficiary)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 47.049,62
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 57.851,15
Background
The service activities in the frame of the project BIS/00/022/014 started at DECOM in Slovakia (Consultant premises).
Countries:
Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 180.000,00
1) Background
The OSA contract to this project bridged the time to continue without interruption the On-Site-Activity of the Western Utility RWE.
Countries:
Armenia, Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 28.992,21
Background
Countries:
Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 472.181,80
1) Background
Countries:
Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 301.441,78
1) Background
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 1.560.041,52
Background
Kola NPP located in Murmansk Oblast in north western Russia comprised 4 power units of VVER 440 type reactors. Unit 1 is in operation since 1973, unit 2 since 1974, unit 3 since 1982 and unit 4 since 1984.
Countries:
Russia
Programme:
TACIS
Budget year:
1999
Amount:
€ 1.090.000,00
R2.01/99 - Phare specific and Kola Units 3&4 specific qualification of Bubble condenser test facility at Elektrogorsk and performance of relevant tests
Objective