Background
Search
6 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove EDF (Electricite de France) filter EDF (Electricite de France) (4)
- (-) Remove SOGIN (Societa Gestione Impianti Nucleari) filter SOGIN (Societa Gestione Impianti Nucleari) (1)
- (-) Remove VT Nuclear Services filter VT Nuclear Services (1)
- Suez Tractebel (3) Apply Suez Tractebel filter
- AMEC (2) Apply AMEC filter
- RRCKI ( Russian Research Centre Kurchatov Institute) (2) Apply RRCKI ( Russian Research Centre Kurchatov Institute) filter
- BERRY (1) Apply BERRY filter
- British Energy (1) Apply British Energy filter
- KGG (Kernkraftwerk Gundremmingen) (1) Apply KGG (Kernkraftwerk Gundremmingen) filter
- Magnox Electric (1) Apply Magnox Electric filter
- PwC (PricewaterhouseCoopers) (1) Apply PwC (PricewaterhouseCoopers) filter
- RE (Rheinisch-Westfälisches Elektrizitätswerk) (1) Apply RE (Rheinisch-Westfälisches Elektrizitätswerk) filter
Contract information field: Sector
Contract information field: Types of activities
- (-) Remove Euratom Loan Preparation filter Euratom Loan Preparation (3)
- (-) Remove On Site Assistance filter On Site Assistance (3)
- Equipment Supply (1) Apply Equipment Supply filter
- Training (1) Apply Training filter
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 49.750,00
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 41.155,00
Background
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 149.780,00
Objective
The objective is to provide assistance to Rosenergoatom (REA) by setting up a complete Project Management Structure (PMS) for completion and upgrading the NPP Kalinin unit 3.
This structure was intended to cover:
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 1.175.443,18
Objectives
Countries:
Russia
Programme:
TACIS
Budget year:
2000
Amount:
€ 114.416,06
Bilibino NPP
Bilibino nuclear power and district heating plant (NPDHP) was the first nuclear power station built beyond the Polar Circle in the central part of the Chukotka peninsula, and it provides electricity for the regional mining and gold mining industries.
Countries:
Russia
Programme:
TACIS
Budget year:
2000
Amount:
€ 1.316.346,00
Objectives