Background
Search
6 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- (-) Remove 2012 filter 2012 (6)
- 2007 (2) Apply 2007 filter
- 2006 (2) Apply 2006 filter
- 2005 (1) Apply 2005 filter
- 2003 (2) Apply 2003 filter
- (-) Remove 2002 filter 2002 (6)
- (-) Remove 2001 filter 2001 (6)
- 2000 (1) Apply 2000 filter
- 1999 (2) Apply 1999 filter
- 1998 (2) Apply 1998 filter
- 1997 (6) Apply 1997 filter
- 1996 (14) Apply 1996 filter
- 1995 (6) Apply 1995 filter
- 1994 (15) Apply 1994 filter
- 1993 (3) Apply 1993 filter
- 1992 (18) Apply 1992 filter
Contract information field: Status
- (-) Remove Closed filter Closed (6)
Contract information field: Contractor
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Kalinin filter Kalinin (3)
- (-) Remove Khmelnitsky filter Khmelnitsky (3)
- Balakovo (5) Apply Balakovo filter
- Zaporozhye (5) Apply Zaporozhye filter
- Chernobyl (4) Apply Chernobyl filter
- Rovno (4) Apply Rovno filter
- South Ukraine (4) Apply South Ukraine filter
- Beloyarsk (2) Apply Beloyarsk filter
- Aktau (1) Apply Aktau filter
- Leningrad (Sosnovy Bor) (1) Apply Leningrad (Sosnovy Bor) filter
- Medzamor (1) Apply Medzamor filter
- Novovoronezh (1) Apply Novovoronezh filter
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
2002
Amount:
€ 5.699.990,17
Countries:
Russia
Programme:
TACIS
Budget year:
2002
Amount:
€ 2.684.733,00
Background
Countries:
Ukraine
Programme:
TACIS
Budget year:
2002
Amount:
€ 676.013,89
1) Background
This project dealt with TACIS OSA (On-Site Assistance) at Khmelnitsky NPP.
Countries:
Ukraine
Programme:
TACIS
Budget year:
2001
Amount:
€ 988.837,31
Objectives
Countries:
Ukraine
Programme:
TACIS
Budget year:
2001
Amount:
€ 2.519.904,60
2.3.1 Introduction
Beneficiary /location:SNRCU – State Nuclear Regulatory Committee of Ukraiine/ Kiev - Ukraine
Main contractor: RISKAUDIT IRSN/GRS International (GEIE)
Countries:
Russia
Programme:
TACIS
Budget year:
2002
Amount:
€ 2.904.491,58
1. Background