Objective
The aim of the project was to control the tritium release and migration in the environment during normal operation and in case of accidents.
Navigation path
Objective
The aim of the project was to control the tritium release and migration in the environment during normal operation and in case of accidents.
Background
Objective
This project consists of replacement of the current 2 (two) booster pumps for the feed water pumps in one Balakovo NPP.
Result
This project was combined with project R1.02/96A and jointly tendered, contracted and supplied.
Objective
This project consists of replacement of the current 2 (two) booster pumps for the feed water pumps in one Balakovo NPP.
Result
This project was combined with project R1.02/95G and jointly tendered, contracted and supplied.
Background
This project is a continuation and extension of a previous TACIS project R5.02/96 (see contract 24943 for the relevant background).
Objective
Only general contract information available.