Objectives
Search
3 results recovered
Contract information field: Programme
Contract information field: Country
- (-) Remove Armenia filter Armenia (3)
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
- (-) Remove Restricted Call for Tender filter Restricted Call for Tender (2)
- (-) Remove Negotiated Procedure filter Negotiated Procedure (1)
- Direct Agreement (3) Apply Direct Agreement filter
- Open Call for Tender (2) Apply Open Call for Tender filter
Countries:
Armenia
Programme:
TACIS
Budget year:
2000
Amount:
€ 925.000,00
Countries:
Armenia
Programme:
TACIS
Budget year:
2000
Amount:
€ 482.600,00
The LBB (Leak Before Break) project was a part of the OSA project activities for Medzamor NPP unit 2. The on site utility in Medzamor NPP during the project was Sogin. The Contractor of the LBB/LDS project was Ansaldo Energia in consortium with Empresarios Agrupados and KONEXP (Russia).
Countries:
Armenia
Programme:
TACIS
Budget year:
2000
Amount:
€ 959.180,00
Objective
This project aimed at replacing the obsolete radiological Instrumentation and increase capability of the plant radiation monitoring system.
Result