Background
Search
3 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Kalinin filter Kalinin (2)
- (-) Remove Smolensk filter Smolensk (1)
- Medzamor (9) Apply Medzamor filter
- Zaporozhye (9) Apply Zaporozhye filter
- Chernobyl (6) Apply Chernobyl filter
- Novovoronezh (4) Apply Novovoronezh filter
- Kola (3) Apply Kola filter
- Beloyarsk (2) Apply Beloyarsk filter
- Khmelnitsky (2) Apply Khmelnitsky filter
- Rovno (2) Apply Rovno filter
- Aktau (1) Apply Aktau filter
- Balakovo (1) Apply Balakovo filter
- South Ukraine (1) Apply South Ukraine filter
Contract information field: Nature
Contract information field: Method of procurement
- (-) Remove Negotiated Procedure filter Negotiated Procedure (3)
- Special Fund (Procurement Agent) (51) Apply Special Fund (Procurement Agent) filter
- Direct Agreement (26) Apply Direct Agreement filter
- Open Call for Tender (7) Apply Open Call for Tender filter
- Informal Consultation (4) Apply Informal Consultation filter
- Restricted Call for Tender (3) Apply Restricted Call for Tender filter
- Competitive Dialogue (1) Apply Competitive Dialogue filter
Countries:
Russia
Programme:
INSC
Budget year:
2009
Amount:
€ 954.598,61
Countries:
Russia
Programme:
TACIS
Budget year:
2006
Amount:
€ 370.000,00
Project Background
Appropriate water chemistry of both primary (nuclear) and secondary (non-nuclear) cooling circuits of a nuclear power plant is necessary to maintain safe, reliable and economical operation of the plant. Among others, it helps to
Countries:
Russia
Programme:
INSC
Budget year:
2007
Amount:
€ 1.469.819,16
Project Description
1 Introduction