Beneficiary Organisation: Goskomatom - beneficiary, ChNPP and Kiev Energoproject, other Ukrainian national authorities
Search
5 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- 2013 (1) Apply 2013 filter
- 2012 (3) Apply 2012 filter
- 2011 (4) Apply 2011 filter
- 2010 (3) Apply 2010 filter
- 2009 (3) Apply 2009 filter
- 2008 (6) Apply 2008 filter
- 2007 (6) Apply 2007 filter
- 2006 (6) Apply 2006 filter
- 2005 (4) Apply 2005 filter
- 2004 (12) Apply 2004 filter
- 2003 (8) Apply 2003 filter
- 2002 (2) Apply 2002 filter
- 2001 (2) Apply 2001 filter
- 2000 (3) Apply 2000 filter
- 1999 (3) Apply 1999 filter
- 1998 (6) Apply 1998 filter
- 1997 (5) Apply 1997 filter
- 1996 (20) Apply 1996 filter
- 1995 (7) Apply 1995 filter
- 1994 (26) Apply 1994 filter
- 1993 (9) Apply 1993 filter
- (-) Remove 1992 filter 1992 (5)
- 1991 (19) Apply 1991 filter
Contract information field: Status
Contract information field: Contractor
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Kola filter Kola (4)
- (-) Remove Novovoronezh filter Novovoronezh (2)
- (-) Remove Chernobyl filter Chernobyl (1)
- (-) Remove Aktau filter Aktau (0)
- Kalinin (18) Apply Kalinin filter
- South Ukraine (16) Apply South Ukraine filter
- Zaporozhye (9) Apply Zaporozhye filter
- Rovno (8) Apply Rovno filter
- Balakovo (7) Apply Balakovo filter
- Dukovany (5) Apply Dukovany filter
- Kozloduy (5) Apply Kozloduy filter
- Smolensk (5) Apply Smolensk filter
- Paks (4) Apply Paks filter
- Bohunice (3) Apply Bohunice filter
- Leningrad (Sosnovy Bor) (3) Apply Leningrad (Sosnovy Bor) filter
- Beloyarsk (2) Apply Beloyarsk filter
- Krsko (1) Apply Krsko filter
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 1.573.024,31
Countries:
Russia
Programme:
TACIS
Budget year:
1992
Amount:
€ 776.962,50
Objective
The overall project aimed to develop and deliver simulation tools to be installed on the VVER-440-NPP sites (230/213). Multifunctional Simulators (MFS) had to be supplied and delivered to Novoronezh Training Centre and Kola NPP.
Countries:
Russia
Programme:
TACIS
Budget year:
1992
Amount:
€ 33.320,38
Background / Objective
Countries:
Russia
Programme:
TACIS
Budget year:
1992
Amount:
€ 403.843,00
Objective
The objective of the project was to implement the on-site assistance (OSA) at Kola NPP by a Western Consultant. This assistance by the Consultant was the subject of a formal contract between EC and the Consultant.
Result
Countries:
Russia
Programme:
TACIS
Budget year:
1992
Amount:
€ 2.259.615,00
Objective
The objective of this project was to prepare the basic design for the modernization of the Reactor Protection System on Units 3 and 4.
Result