Objective
Search
Contract information field: Programme
- (-) Remove TACIS filter TACIS (23)
Contract information field: Country
Contract information field: Budget year
- 2005 (3) Apply 2005 filter
- 2003 (2) Apply 2003 filter
- 2002 (2) Apply 2002 filter
- 2001 (4) Apply 2001 filter
- 1999 (2) Apply 1999 filter
- 1998 (3) Apply 1998 filter
- 1997 (12) Apply 1997 filter
- (-) Remove 1996 filter 1996 (23)
- 1995 (21) Apply 1995 filter
- (-) Remove 1994 filter 1994 (23)
- 1993 (4) Apply 1993 filter
- 1992 (18) Apply 1992 filter
Contract information field: Status
Contract information field: Contractor
- Bopp & Reuther (2) Apply Bopp & Reuther filter
- Datost (2) Apply Datost filter
- IBL (2) Apply IBL filter
- INKLA (2) Apply INKLA filter
- KSC Anlagenbau (Kraftswerk - Service Cottbus) (2) Apply KSC Anlagenbau (Kraftswerk - Service Cottbus) filter
- SEMPELL AG (2) Apply SEMPELL AG filter
- DataLoop (1) Apply DataLoop filter
- Dtn (Desarrollo Tecnologico Nuclear) (1) Apply Dtn (Desarrollo Tecnologico Nuclear) filter
- EDF (Electricite de France) (1) Apply EDF (Electricite de France) filter
- EFCO (1) Apply EFCO filter
- Enprima Engineering Oy (1) Apply Enprima Engineering Oy filter
- GEMCO (1) Apply GEMCO filter
- Huntsman (1) Apply Huntsman filter
- NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) (1) Apply NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) filter
- NIKIMT (Institute of Assembly Technology) (1) Apply NIKIMT (Institute of Assembly Technology) filter
- Rohm & Haas (1) Apply Rohm & Haas filter
- SEMA Group (1) Apply SEMA Group filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove South Ukraine filter South Ukraine (18)
- (-) Remove Beloyarsk filter Beloyarsk (5)
- Kalinin (26) Apply Kalinin filter
- Zaporozhye (22) Apply Zaporozhye filter
- Novovoronezh (20) Apply Novovoronezh filter
- Balakovo (17) Apply Balakovo filter
- Medzamor (13) Apply Medzamor filter
- Kola (10) Apply Kola filter
- Rovno (9) Apply Rovno filter
- Chernobyl (8) Apply Chernobyl filter
- Smolensk (8) Apply Smolensk filter
- Aktau (7) Apply Aktau filter
- Leningrad (Sosnovy Bor) (5) Apply Leningrad (Sosnovy Bor) filter
- Khmelnitsky (3) Apply Khmelnitsky filter
Contract information field: Nature
Contract information field: Method of procurement
Objectives
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Beneficiary Organisation: Energoatom
1) Background
Beneficiary Organisation: Energoatom
1) Background
Objectives
Objectives
Objectives
Objectives
1) Background
Background
Objective
The aim of the project is the refurbishment of the present Process Monitoring System (PMS) with full consideration of the possibility to operate with PMS functions in the present as well as in the new system.
Background
This project is part of the Reactor Pressure Vessel In-Service Inspection Project U1.02/92A.
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needed support for improvement of its maintenance system: maintenance management was not performed according to modern practice.
2) Objectives
Objective
According to the intention of the European Union and the Russian Ministry of Atomic Power the operational safety assistance, which started with TACIS 92, continued with TACIS 94 with the same Western and Eastern Utility and NPPs.
1) Background
Continuation of TACIS OSA (On-Site Assistance) at South Ukraine NPP.