Objective:
Overall Objective
Navigation path
Objective:
Overall Objective
Objective
The objective of the project was to implement the on-site assistance (OSA) at Kola NPP by a Western Consultant. This assistance by the Consultant was the subject of a formal contract between EC and the Consultant.
Result
Objective
The objective of this project was to prepare the basic design for the modernization of the Reactor Protection System on Units 3 and 4.
Result
Objective (phase 2)
The objective of this project was to continue the work started in a first phase under the same project number. This project is to be seen as a contractual extension of the previous one with the same number R1.06/7/92.
Result
Background / Objective
Objective
Objective
The project’s objective covered research, design, supply and commissioning of:
Objective
On request of the Beneficiary a simulator (see Project R1.06/93) was provided for instruction and proficiency training of operator teams to improve their skills and knowledge to operate the BN 600 NPP at Beloyarsk.
Objective R1.01/93
This On-Site-Assistance, in short “OSA”, project deals with the increase of the safety culture on the NPP. As in all other cases the OSA was performed by an EU utility, working with a team of Western and Russian experts.
Objectives
The objective of the Tacis project consists in providing technical support to Gosatomnadzor of RF in its safety evaluation of the Kola units 3 & 4 upgrading Instrumentation and Control programme.
Background
Project Description
Background
Objectives
Objective
Objective
Objective
Background
Kola NPP located in Murmansk Oblast in north western Russia comprised 4 power units of VVER 440 type reactors. Unit 1 is in operation since 1973, unit 2 since 1974, unit 3 since 1982 and unit 4 since 1984.
Background