1) Background
Search
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- 2007 (6) Apply 2007 filter
- 2006 (3) Apply 2006 filter
- (-) Remove 2005 filter 2005 (15)
- 2003 (1) Apply 2003 filter
- 2002 (3) Apply 2002 filter
- 1997 (17) Apply 1997 filter
- (-) Remove 1996 filter 1996 (15)
- 1995 (13) Apply 1995 filter
- 1994 (12) Apply 1994 filter
- 1993 (15) Apply 1993 filter
- 1992 (9) Apply 1992 filter
Contract information field: Status
Contract information field: Contractor
- SEMPELL AG (3) Apply SEMPELL AG filter
- Brühl&Kjaer (1) Apply Brühl&Kjaer filter
- EFCO (1) Apply EFCO filter
- Framatome (1) Apply Framatome filter
- HK (Hahn & Kolb) (1) Apply HK (Hahn & Kolb) filter
- IBL (1) Apply IBL filter
- Lisega (1) Apply Lisega filter
- PRORAS SRL (1) Apply PRORAS SRL filter
- Radiy (1) Apply Radiy filter
- SEMA Group (1) Apply SEMA Group filter
- svt Brandschutz (1) Apply svt Brandschutz filter
- VHB Germany (1) Apply VHB Germany filter
- Werner Riester (1) Apply Werner Riester filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Zaporozhye filter Zaporozhye (10)
- (-) Remove Beloyarsk filter Beloyarsk (3)
- (-) Remove Khmelnitsky filter Khmelnitsky (2)
- Medzamor (9) Apply Medzamor filter
- Novovoronezh (9) Apply Novovoronezh filter
- Balakovo (6) Apply Balakovo filter
- South Ukraine (6) Apply South Ukraine filter
- Kalinin (3) Apply Kalinin filter
- Kola (3) Apply Kola filter
- Rovno (3) Apply Rovno filter
- Leningrad (Sosnovy Bor) (1) Apply Leningrad (Sosnovy Bor) filter
- Smolensk (1) Apply Smolensk filter
Contract information field: Nature
Contract information field: Method of procurement
1) Background
1) Background
1) Background
1) Background
Background
1) Background
Objective
The aim of the project is the refurbishment of the present Process Monitoring System (PMS) with full consideration of the possibility to operate with PMS functions in the present as well as in the new system.
1) Background
The issue of the integrity of the cable penetrations in relation to fire was identified by the IAEA and ranked level 3. Moreover, the ZNPP received in 1995 a licence conditions for operation from SNRC.
Beneficiary Organisation: Energoatom
1) Background
Beneficiary Organisation: Energoatom
1) Background
Background
Objectives
Background
Objectives
In the framework of the Tacis Nuclear Safety Programme, it was decided to increase the nuclear safety of the units 1 through 6 at the Zaporozhye NPP by improving the protection of the primary circuit from overpressure under normal and emergency modes.