Objectives
The present TACIS project U1.01/95C aims at replacing the 12 SG (steam generator) safety valves (2 per SG) of each unit 1 and unit 2 of Rovno NPP. The new safety valves should have the following functions:
Search
5 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove SEMA Group filter SEMA Group (3)
- (-) Remove Bopp & Reuther filter Bopp & Reuther (2)
- EDF (Electricite de France) (17) Apply EDF (Electricite de France) filter
- Framatome (5) Apply Framatome filter
- NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) (3) Apply NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) filter
- Riskaudit (3) Apply Riskaudit filter
- Intercontrole (2) Apply Intercontrole filter
- RE (Rheinisch-Westfälisches Elektrizitätswerk) (2) Apply RE (Rheinisch-Westfälisches Elektrizitätswerk) filter
- SEBIM (2) Apply SEBIM filter
- SEMPELL AG (2) Apply SEMPELL AG filter
- Siemens (2) Apply Siemens filter
- SOGIN (Societa Gestione Impianti Nucleari) (2) Apply SOGIN (Societa Gestione Impianti Nucleari) filter
- Alstom (1) Apply Alstom filter
- Babcock Sempell (1) Apply Babcock Sempell filter
- Brühl&Kjaer (1) Apply Brühl&Kjaer filter
- DataLoop (1) Apply DataLoop filter
- EFCO (1) Apply EFCO filter
- ENVINET (1) Apply ENVINET filter
- FLIR (1) Apply FLIR filter
- Fortum (1) Apply Fortum filter
- Geholit (1) Apply Geholit filter
- Herion (1) Apply Herion filter
- Lisega (1) Apply Lisega filter
- Nukem (1) Apply Nukem filter
- Olivetti (1) Apply Olivetti filter
- Onet Technologies (1) Apply Onet Technologies filter
- Persta (1) Apply Persta filter
- Pribori Oy (1) Apply Pribori Oy filter
- PRORAS SRL (1) Apply PRORAS SRL filter
- Rados (1) Apply Rados filter
- SDEC (1) Apply SDEC filter
- Syseca (1) Apply Syseca filter
- Weir Valves & Controls (1) Apply Weir Valves & Controls filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 65.746,66
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 995.822,00
Objective
The aim of the project is the refurbishment of the present Process Monitoring System (PMS) with full consideration of the possibility to operate with PMS functions in the present as well as in the new system.
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 6.060,00
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 80’s, there was an urgent need for spare parts in order to allow operation of Ukrainian NPPs.
Countries:
Russia
Programme:
TACIS
Budget year:
1997
Amount:
€ 278.160,00
Beloyarsk Process Monitoring System (see projects R1.06/95E and R1.06/96B)
Countries:
Russia
Programme:
TACIS
Budget year:
1995
Amount:
€ 626.124,00
See projects R1.06/97D and�R1.06/96B