Objective
Search
9 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove EDF (Electricite de France) filter EDF (Electricite de France) (6)
- (-) Remove SDEC filter SDEC (1)
- (-) Remove SEMPELL AG filter SEMPELL AG (1)
- (-) Remove Siemens filter Siemens (1)
- NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) (3) Apply NERSA (Centrale Nucleaire Europeenne a Neutrons Rapides) filter
- SEMA Group (3) Apply SEMA Group filter
- Framatome (2) Apply Framatome filter
- SOGIN (Societa Gestione Impianti Nucleari) (2) Apply SOGIN (Societa Gestione Impianti Nucleari) filter
- APAT (Agenzia per la protezione dell ambiente e per i servizi tecnici) (1) Apply APAT (Agenzia per la protezione dell ambiente e per i servizi tecnici) filter
- AVN (1) Apply AVN filter
- DataLoop (1) Apply DataLoop filter
- Earth Data Limited-UK (1) Apply Earth Data Limited-UK filter
- EFCO (1) Apply EFCO filter
- ENEA (1) Apply ENEA filter
- EPTISA (1) Apply EPTISA filter
- FLIR (1) Apply FLIR filter
- Fortum (1) Apply Fortum filter
- GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) (1) Apply GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) filter
- IRSN (Institut de Radioprotection et de Surete Nucleaire) (1) Apply IRSN (Institut de Radioprotection et de Surete Nucleaire) filter
- NRG (Nuclear Research and Consultancy Group) (1) Apply NRG (Nuclear Research and Consultancy Group) filter
- OGS (1) Apply OGS filter
- Olivetti (1) Apply Olivetti filter
- Pribori Oy (1) Apply Pribori Oy filter
- PRORAS SRL (1) Apply PRORAS SRL filter
- Riskaudit (1) Apply Riskaudit filter
- STUK (Sateilyturvakeskus) (1) Apply STUK (Sateilyturvakeskus) filter
- University of Leoben (1) Apply University of Leoben filter
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Beloyarsk filter Beloyarsk (9)
- (-) Remove Krsko filter Krsko (0)
- Rovno (13) Apply Rovno filter
- Kozloduy (12) Apply Kozloduy filter
- Zaporozhye (12) Apply Zaporozhye filter
- Dukovany (9) Apply Dukovany filter
- Balakovo (5) Apply Balakovo filter
- South Ukraine (5) Apply South Ukraine filter
- Aktau (4) Apply Aktau filter
- Bohunice (4) Apply Bohunice filter
- Kalinin (4) Apply Kalinin filter
- Kola (3) Apply Kola filter
- Paks (3) Apply Paks filter
- Novovoronezh (2) Apply Novovoronezh filter
- Leningrad (Sosnovy Bor) (1) Apply Leningrad (Sosnovy Bor) filter
- Mochovce (1) Apply Mochovce filter
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
1992
Amount:
€ 167.577,77
Countries:
Russia
Programme:
TACIS
Budget year:
1993
Amount:
€ 487.664,87
Objective
The project’s objective covered research, design, supply and commissioning of:
Countries:
Russia
Programme:
TACIS
Budget year:
2002
Amount:
€ 1.632.650,61
Project Description
Countries:
Russia
Programme:
TACIS
Budget year:
1996
Amount:
€ 1.175.443,18
Objectives
Countries:
Russia
Programme:
TACIS
Budget year:
1997
Amount:
€ 595.491,42
Objective
Countries:
Russia
Programme:
TACIS
Budget year:
1998
Amount:
€ 700.000,00
Objective
Countries:
Russia
Programme:
TACIS
Budget year:
2005
Amount:
€ 9.318.912,00
Background
Countries:
Russia
Programme:
TACIS
Budget year:
1993
Amount:
€ 3.399.366,00
Objective
A simulator was to be provided for instruction and proficiency training of operator teams to improve their skills and knowledge.
The simulator had to provide the following types of training:
Countries:
Russia
Programme:
TACIS
Budget year:
1995
Amount:
€ 49.117,18
Objective
The aim of the project was to control the tritium release and migration in the environment during normal operation and in case of accidents.