Background
The TACIS programmes for Nuclear Safety agreed upon between the European Commission and the relevant authorities of beneficiary states contained provisions for on-site assistance (OSA).
Search
3 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove MGPI (Mirion Technologies) filter MGPI (Mirion Technologies) (1)
- (-) Remove RRCKI ( Russian Research Centre Kurchatov Institute) filter RRCKI ( Russian Research Centre Kurchatov Institute) (1)
- (-) Remove SEBIM filter SEBIM (1)
- Framatome (1) Apply Framatome filter
- Nukem (1) Apply Nukem filter
- TUV NORD (1) Apply TUV NORD filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
- (-) Remove Rosenergoatom filter Rosenergoatom (3)
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Russia
Programme:
TACIS
Budget year:
1994
Amount:
€ 475.616,96
Countries:
Russia
Programme:
TACIS
Budget year:
1994
Amount:
€ 1.604.749,00
Background
The aim of the on-site assistance (OSA) Large scale project for Kola NPP was to maintain a strong EU engagement in order to support the country efforts to deal with problems inherited from the past in the context of on-going budget difficulties.
Countries:
Russia
Programme:
TACIS
Budget year:
1994
Amount:
€ 1.250.000,00