1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 80’s, there was an urgent need for spare parts in order to allow operation of Ukrainian NPPs.
Search
5 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove Bopp & Reuther filter Bopp & Reuther (3)
- (-) Remove SEMPELL AG filter SEMPELL AG (1)
- (-) Remove Technoserv filter Technoserv (1)
- EDF (Electricite de France) (11) Apply EDF (Electricite de France) filter
- Riskaudit (9) Apply Riskaudit filter
- SOGIN (Societa Gestione Impianti Nucleari) (6) Apply SOGIN (Societa Gestione Impianti Nucleari) filter
- Framatome (4) Apply Framatome filter
- UJV Rez (Nuclear Research Institute Rez) (4) Apply UJV Rez (Nuclear Research Institute Rez) filter
- VUEZ (4) Apply VUEZ filter
- SEBIM (3) Apply SEBIM filter
- Alstom (2) Apply Alstom filter
- Ansaldo Energia (2) Apply Ansaldo Energia filter
- Intercontrole (2) Apply Intercontrole filter
- Nukem (2) Apply Nukem filter
- RE (Rheinisch-Westfälisches Elektrizitätswerk) (2) Apply RE (Rheinisch-Westfälisches Elektrizitätswerk) filter
- All Trade Italy (1) Apply All Trade Italy filter
- Babcock Sempell (1) Apply Babcock Sempell filter
- BALTIJOS INFORMACINES SISTEMOS UAB (1) Apply BALTIJOS INFORMACINES SISTEMOS UAB filter
- Belgatom (1) Apply Belgatom filter
- Brühl&Kjaer (1) Apply Brühl&Kjaer filter
- CAG TECHNOLOGIE MANAGEMENT CONSULTANTS GREIFSWALD GMBH (1) Apply CAG TECHNOLOGIE MANAGEMENT CONSULTANTS GREIFSWALD GMBH filter
- Canberra (1) Apply Canberra filter
- Data Systems & Solutions (1) Apply Data Systems & Solutions filter
- Diakont (1) Apply Diakont filter
- ENCO - Enconet (1) Apply ENCO - Enconet filter
- ENVINET (1) Apply ENVINET filter
- Geholit (1) Apply Geholit filter
- Herion (1) Apply Herion filter
- Impulse (Severodonetsk Research and Production Association) (1) Apply Impulse (Severodonetsk Research and Production Association) filter
- INETEC (Institut za Nuklearnu Tehnologiju) (1) Apply INETEC (Institut za Nuklearnu Tehnologiju) filter
- INKOR (1) Apply INKOR filter
- ITER-Consult (Independent Technical Evaluation and Review) (1) Apply ITER-Consult (Independent Technical Evaluation and Review) filter
- Lisega (1) Apply Lisega filter
- MGPI (Mirion Technologies) (1) Apply MGPI (Mirion Technologies) filter
- Na-Na (1) Apply Na-Na filter
- Onet Technologies (1) Apply Onet Technologies filter
- Persta (1) Apply Persta filter
- Pilosio (1) Apply Pilosio filter
- Rados (1) Apply Rados filter
- RISK ENGINEERING AD (1) Apply RISK ENGINEERING AD filter
- SAMI (1) Apply SAMI filter
- Schneider Electric (1) Apply Schneider Electric filter
- Siemens (1) Apply Siemens filter
- Skoda (1) Apply Skoda filter
- Suez Tractebel (1) Apply Suez Tractebel filter
- svt Brandschutz (1) Apply svt Brandschutz filter
- Syseca (1) Apply Syseca filter
- VF (1) Apply VF filter
- VNIIAES (1) Apply VNIIAES filter
- VT Nuclear Services (1) Apply VT Nuclear Services filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Rovno filter Rovno (3)
- (-) Remove Bilibino filter Bilibino (1)
- (-) Remove Medzamor filter Medzamor (1)
- Zaporozhye (12) Apply Zaporozhye filter
- South Ukraine (10) Apply South Ukraine filter
- Balakovo (3) Apply Balakovo filter
- Beloyarsk (1) Apply Beloyarsk filter
- Novovoronezh (1) Apply Novovoronezh filter
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 6.060,00
Countries:
Armenia
Programme:
TACIS
Budget year:
1996
Amount:
€ 921.302,00
Objectives
Countries:
Russia
Programme:
TACIS
Budget year:
2003
Amount:
€ 1.045.000,00
Bilibino NPP
Bilibino nuclear power and district heating plant (NPDHP) was the first nuclear power station built beyond the Polar Circle in the central part of the Chukotka peninsula, and it provides electricity for the regional mining and gold mining industries.
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 65.746,66
Objectives
The present TACIS project U1.01/95C aims at replacing the 12 SG (steam generator) safety valves (2 per SG) of each unit 1 and unit 2 of Rovno NPP. The new safety valves should have the following functions:
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 126.289,00
Objectives
The present TACIS project U1.01/96C aims at providing spare parts for valves for unit 3 pressuriser and pressure accumulators, which were originally supplied by German companies Sempell and Bopp & Reuther.
Background