1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 80’s, there was an urgent need for spare parts in order to allow operation of Ukrainian NPPs.
Search
4 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove Bopp & Reuther filter Bopp & Reuther (2)
- (-) Remove Babcock Sempell filter Babcock Sempell (1)
- (-) Remove Technoserv filter Technoserv (1)
- EDF (Electricite de France) (11) Apply EDF (Electricite de France) filter
- Framatome (3) Apply Framatome filter
- Intercontrole (2) Apply Intercontrole filter
- RE (Rheinisch-Westfälisches Elektrizitätswerk) (2) Apply RE (Rheinisch-Westfälisches Elektrizitätswerk) filter
- Riskaudit (2) Apply Riskaudit filter
- SEBIM (2) Apply SEBIM filter
- Alstom (1) Apply Alstom filter
- Brühl&Kjaer (1) Apply Brühl&Kjaer filter
- ENVINET (1) Apply ENVINET filter
- Geholit (1) Apply Geholit filter
- Herion (1) Apply Herion filter
- Lisega (1) Apply Lisega filter
- Nukem (1) Apply Nukem filter
- Onet Technologies (1) Apply Onet Technologies filter
- Persta (1) Apply Persta filter
- Rados (1) Apply Rados filter
- Schneider Electric (1) Apply Schneider Electric filter
- SEMPELL AG (1) Apply SEMPELL AG filter
- Siemens (1) Apply Siemens filter
- SOGIN (Societa Gestione Impianti Nucleari) (1) Apply SOGIN (Societa Gestione Impianti Nucleari) filter
- Syseca (1) Apply Syseca filter
- Weir Valves & Controls (1) Apply Weir Valves & Controls filter
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 6.060,00
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 1.239.203,21
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 80’s, there was an urgent need for spare parts in order to allow operation of Ukrainian NPPs.
Countries:
Russia
Programme:
TACIS
Budget year:
2003
Amount:
€ 1.045.000,00
Bilibino NPP
Bilibino nuclear power and district heating plant (NPDHP) was the first nuclear power station built beyond the Polar Circle in the central part of the Chukotka peninsula, and it provides electricity for the regional mining and gold mining industries.
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 65.746,66
Objectives
The present TACIS project U1.01/95C aims at replacing the 12 SG (steam generator) safety valves (2 per SG) of each unit 1 and unit 2 of Rovno NPP. The new safety valves should have the following functions: