1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 80’s, there was an urgent need for spare parts in order to allow operation of Ukrainian NPPs.
Search
5 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- (-) Remove Westinghouse filter Westinghouse (2)
- (-) Remove Adams filter Adams (1)
- (-) Remove Riskaudit filter Riskaudit (1)
- (-) Remove SOGIN (Societa Gestione Impianti Nucleari) filter SOGIN (Societa Gestione Impianti Nucleari) (1)
- Bopp & Reuther (5) Apply Bopp & Reuther filter
- Dtn (Desarrollo Tecnologico Nuclear) (5) Apply Dtn (Desarrollo Tecnologico Nuclear) filter
- KSC Anlagenbau (Kraftswerk - Service Cottbus) (5) Apply KSC Anlagenbau (Kraftswerk - Service Cottbus) filter
- SEMPELL AG (5) Apply SEMPELL AG filter
- Datost (3) Apply Datost filter
- IBL (3) Apply IBL filter
- INKLA (3) Apply INKLA filter
- Suez Tractebel (3) Apply Suez Tractebel filter
- NIKIMT (Institute of Assembly Technology) (2) Apply NIKIMT (Institute of Assembly Technology) filter
- Persta (2) Apply Persta filter
- Tecnatom (2) Apply Tecnatom filter
- UNESA (Asociacion Espanola de la Industria Electrica) (2) Apply UNESA (Asociacion Espanola de la Industria Electrica) filter
- ABB (Asea Brown Boveri) (1) Apply ABB (Asea Brown Boveri) filter
- Albrich (1) Apply Albrich filter
- All Trade Italy (1) Apply All Trade Italy filter
- Areva (1) Apply Areva filter
- Babcock Sempell (1) Apply Babcock Sempell filter
- BOLT (1) Apply BOLT filter
- Brühl&Kjaer (1) Apply Brühl&Kjaer filter
- Dantec (1) Apply Dantec filter
- Deugro (1) Apply Deugro filter
- Elox-Prom (1) Apply Elox-Prom filter
- ELTA (1) Apply ELTA filter
- Enprima Engineering Oy (1) Apply Enprima Engineering Oy filter
- GEMCO (1) Apply GEMCO filter
- Gossen (1) Apply Gossen filter
- Herion (1) Apply Herion filter
- Huntsman (1) Apply Huntsman filter
- Iberdrola (1) Apply Iberdrola filter
- Jansen (1) Apply Jansen filter
- MOSTRO (1) Apply MOSTRO filter
- Rohm & Haas (1) Apply Rohm & Haas filter
- Schneider Electric (1) Apply Schneider Electric filter
- Seitz (1) Apply Seitz filter
- svt Brandschutz (1) Apply svt Brandschutz filter
- Technoserv (1) Apply Technoserv filter
- VTT (Technical Research Centre of Finland) (1) Apply VTT (Technical Research Centre of Finland) filter
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove South Ukraine filter South Ukraine (4)
- (-) Remove Bilibino filter Bilibino (1)
- Kozloduy (13) Apply Kozloduy filter
- Medzamor (12) Apply Medzamor filter
- Paks (10) Apply Paks filter
- Dukovany (8) Apply Dukovany filter
- Bohunice (7) Apply Bohunice filter
- Ignalina (6) Apply Ignalina filter
- Chernobyl (4) Apply Chernobyl filter
- Beloyarsk (3) Apply Beloyarsk filter
- Kalinin (2) Apply Kalinin filter
- Khmelnitsky (2) Apply Khmelnitsky filter
- Kola (2) Apply Kola filter
- Mochovce (2) Apply Mochovce filter
- Rovno (2) Apply Rovno filter
- Zaporozhye (2) Apply Zaporozhye filter
- Aktau (1) Apply Aktau filter
- Baita Bihor (1) Apply Baita Bihor filter
- Balakovo (1) Apply Balakovo filter
- Novovoronezh (1) Apply Novovoronezh filter
- Smolensk (1) Apply Smolensk filter
Contract information field: Nature
Contract information field: Method of procurement
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 477.297,00
Countries:
Ukraine
Programme:
TACIS
Budget year:
1995
Amount:
€ 302.928,00
Beneficiary organisation: Energoatom, Ukraine
1) Background
South Ukraine NPP needs support for improvement of its documentation management system: it is not performed according to modern practice, which makes difficult to have rigorous and up-to-date operational documentation.
Countries:
Ukraine
Programme:
TACIS
Budget year:
1992
Amount:
€ 3.007.197,00
1)Background
Countries:
Russia
Programme:
TACIS
Budget year:
2000
Amount:
€ 114.416,06
Bilibino NPP
Bilibino nuclear power and district heating plant (NPDHP) was the first nuclear power station built beyond the Polar Circle in the central part of the Chukotka peninsula, and it provides electricity for the regional mining and gold mining industries.
Countries:
Ukraine
Programme:
TACIS
Budget year:
1999
Amount:
€ 898.336,80
Background