Project BE/RA/02 is a follow-up of project BE/RA/01 with almost the same objectives. The assistance in the field of emergency preparedness including planning and training was included as new objective. This project has 6 technical tasks.
Search
7 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
- (-) Remove Government of Ukraine filter Government of Ukraine (6)
- (-) Remove Ministry for Emergency Situations (Belarus) filter Ministry for Emergency Situations (Belarus) (1)
- Rosenergoatom (57) Apply Rosenergoatom filter
- EnergoAtom (24) Apply EnergoAtom filter
- Rostechnadzor (13) Apply Rostechnadzor filter
- Nuclear Regulatory Administration (NRA) of Ukraine (12) Apply Nuclear Regulatory Administration (NRA) of Ukraine filter
- State Nuclear Regulatory Committee of Ukraine (SNRCU) (9) Apply State Nuclear Regulatory Committee of Ukraine (SNRCU) filter
- Armenian Nuclear Power Plant (8) Apply Armenian Nuclear Power Plant filter
- MINATOM RF, later ROSATOM (since 12/2007) (7) Apply MINATOM RF, later ROSATOM (since 12/2007) filter
- Chernobyl NPP (6) Apply Chernobyl NPP filter
- Gosatomnadzor (6) Apply Gosatomnadzor filter
- GOSKOMATOM (6) Apply GOSKOMATOM filter
- GAN (Ukraine) (3) Apply GAN (Ukraine) filter
- Nuclear Regulatory Administration of Armenia (3) Apply Nuclear Regulatory Administration of Armenia filter
- Safety Authorities of Russia (GAN-RF) (3) Apply Safety Authorities of Russia (GAN-RF) filter
- Armenian Nuclear Regulatory Authority (ANRA) (2) Apply Armenian Nuclear Regulatory Authority (ANRA) filter
- Ministry of Emergencies of Ukraine (2) Apply Ministry of Emergencies of Ukraine filter
- Administration of the Exclusion Zone SSE “Technocentre” (1) Apply Administration of the Exclusion Zone SSE “Technocentre” filter
- Emercom of Belarus (1) Apply Emercom of Belarus filter
- Kazakhstan Atomic Energy Committee (KAEC) (1) Apply Kazakhstan Atomic Energy Committee (KAEC) filter
- MEPNS in Ukraine & Ministry of EMERCOM in Belarus (1) Apply MEPNS in Ukraine & Ministry of EMERCOM in Belarus filter
- Ministry of Environmental Protection of Ukraine (1) Apply Ministry of Environmental Protection of Ukraine filter
- Ministry of Fuel and Energy of Ukraine (1) Apply Ministry of Fuel and Energy of Ukraine filter
- NNEGC Energoatom (1) Apply NNEGC Energoatom filter
- whole Ukrainian nuclear sector (1) Apply whole Ukrainian nuclear sector filter
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nature
- (-) Remove Services filter Services (7)
Contract information field: Method of procurement
- (-) Remove Direct Agreement filter Direct Agreement (6)
- (-) Remove Informal Consultation filter Informal Consultation (1)
- Service contracts - International Restricted Procedure with prior publication (7) Apply Service contracts - International Restricted Procedure with prior publication filter
- Single Tender (3) Apply Single Tender filter
- Negotiated Procedure (1) Apply Negotiated Procedure filter
Countries:
Belarus
Programme:
TACIS
Budget year:
1999
Amount:
€ 261.435,97
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 2.698.751,00
See contract 25862 for detailed information
Countries:
Ukraine
Programme:
TACIS
Budget year:
1994
Amount:
€ 228.676,00
[1] The Project Management Group, PMG, is an association between Goskomatom and three European Utilities (EDF, IVO, Tractebel).
1. Background
Countries:
Ukraine
Programme:
TACIS
Budget year:
1994
Amount:
€ 137.275,00
See contract 24090 for more information
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 37.646,00
1) Background
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 3.639.595,00
see contract 25862 for detailed information
Countries:
Ukraine
Programme:
TACIS
Budget year:
1996
Amount:
€ 3.790.545,00
1) Background Ukrainian government was always considering completion and upgrading of 2 VVER units: Rovno-4 and Khmelnitsky-2 (R4K2), whose construction was stopped in the late 80’s.