1) Background The Modernisation Programme for Rovno 4 and Khmelnisky 2 NPPs of VVER 1000 type was developed on behalf of the GOSKOMATOM of UKRAINE by KIEP of Ukraine as General Designer and MOHT, an association of Russian designers, with the participation of Rovno and Khmelnitsky
Search
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- ENCO - Enconet (3) Apply ENCO - Enconet filter
- Crown Agents (2) Apply Crown Agents filter
- Italtrend (2) Apply Italtrend filter
- Lopez Arcos (2) Apply Lopez Arcos filter
- EDF (Electricite de France) (1) Apply EDF (Electricite de France) filter
- GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) (1) Apply GRS (Gesellschaft fur Anlagen und Reaktorsicherheit) filter
- Karuweeg (1) Apply Karuweeg filter
- Riskaudit (1) Apply Riskaudit filter
- VTT (Technical Research Centre of Finland) (1) Apply VTT (Technical Research Centre of Finland) filter
Contract information field: Sector
Contract information field: Types of activities
- (-) Remove Technical expertise filter Technical expertise (10)
- (-) Remove Technical Support Organisations filter Technical Support Organisations (5)
- Design safety (80) Apply Design safety filter
- On Site Assistance (41) Apply On Site Assistance filter
- Waste Management (36) Apply Waste Management filter
- Regulatory Authorities (24) Apply Regulatory Authorities filter
- Equipment Supply (21) Apply Equipment Supply filter
- Training (18) Apply Training filter
- Mitigation of Chernobyl accident (11) Apply Mitigation of Chernobyl accident filter
- Fuel Cycle (7) Apply Fuel Cycle filter
- Studies (7) Apply Studies filter
- Safeguards (4) Apply Safeguards filter
- Support to NPP operators (4) Apply Support to NPP operators filter
- Decommissioning (3) Apply Decommissioning filter
- Emergency Preparedness (3) Apply Emergency Preparedness filter
- RBMK studies (3) Apply RBMK studies filter
- Probabilistic Safety Analysis (2) Apply Probabilistic Safety Analysis filter
- Euratom Loan Preparation (1) Apply Euratom Loan Preparation filter
Contract information field: Partner (Beneficiary)
- MINATOM RF, later ROSATOM (since 12/2007) (2) Apply MINATOM RF, later ROSATOM (since 12/2007) filter
- GOSKOMATOM (1) Apply GOSKOMATOM filter
- Nuclear Regulatory Administration (NRA) of Ukraine (1) Apply Nuclear Regulatory Administration (NRA) of Ukraine filter
- Nuclear Regulatory Administration of Armenia (1) Apply Nuclear Regulatory Administration of Armenia filter
- Rostechnadzor (1) Apply Rostechnadzor filter
Contract information field: Meta geographical zone
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
- (-) Remove Restricted Call for Tender filter Restricted Call for Tender (10)
- (-) Remove Negotiated Procedure filter Negotiated Procedure (5)
- Direct Agreement (87) Apply Direct Agreement filter
- Single Tender (17) Apply Single Tender filter
- Specific contract on Framework contract (4) Apply Specific contract on Framework contract filter
- Informal Consultation (2) Apply Informal Consultation filter
- Competitive Dialogue (1) Apply Competitive Dialogue filter
- Open Call for Tender (1) Apply Open Call for Tender filter
- Service contracts - International Restricted Procedure with prior publication (1) Apply Service contracts - International Restricted Procedure with prior publication filter
Background
Introduction
The project summary will be published after the completion of the project.
The purpose of this contract is for the European Commission to acquire such assistance from the Consultant as may be required to
(1) prepare an evaluation of the INSC programme to date and to
Background
Objectives
Objective
Introduction
In the Memorandum of Understanding between the EC and Minatom, signed in 1995, it was agreed to establish the Joint Management Unit to assist the EC in the facilitation of effective programme and project implementation of the Tacis programme in the nuclear safety field.
Brief Project History
Introduction
Objective
The objective of this project was to assist the GAN-RF and Russian TSOs in reviewing and assessing the accident analysis performed for units 1 and 2 of Kola NPP within project TACIS-91-1.3, further referred to as Industrial Project.
Objective
With this project a technical basis for the qualification of Non Destructive Examination (NDE) was intended to be established in Russia.
The project activities were divided into three (3) different fields of work: