Project Background
Appropriate water chemistry of both primary (nuclear) and secondary (non-nuclear) cooling circuits of a nuclear power plant is necessary to maintain safe, reliable and economical operation of the plant. Among others, it helps to
Search
8 results recovered
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
Contract information field: Status
Contract information field: Contractor
- Riskaudit (3) Apply Riskaudit filter
- UJV Rez (Nuclear Research Institute Rez) (2) Apply UJV Rez (Nuclear Research Institute Rez) filter
- Elektrogorsk Research and Engineering Center on NPP Safety (1) Apply Elektrogorsk Research and Engineering Center on NPP Safety filter
- Suez Tractebel (1) Apply Suez Tractebel filter
- VUJE (1) Apply VUJE filter
Contract information field: Sector
Contract information field: Types of activities
- On Site Assistance (2) Apply On Site Assistance filter
- Design safety (1) Apply Design safety filter
- Regulatory Authorities (1) Apply Regulatory Authorities filter
- Studies (1) Apply Studies filter
- Support to NPP operators (1) Apply Support to NPP operators filter
- Technical Support Organisations (1) Apply Technical Support Organisations filter
Contract information field: Partner (Beneficiary)
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
- (-) Remove Medzamor filter Medzamor (6)
- (-) Remove Kalinin filter Kalinin (2)
- Chernobyl (4) Apply Chernobyl filter
- Zaporozhye (4) Apply Zaporozhye filter
- Khmelnitsky (2) Apply Khmelnitsky filter
- Rovno (2) Apply Rovno filter
- Beloyarsk (1) Apply Beloyarsk filter
- Kola (1) Apply Kola filter
- Novovoronezh (1) Apply Novovoronezh filter
- Smolensk (1) Apply Smolensk filter
- South Ukraine (1) Apply South Ukraine filter
Contract information field: Nature
- (-) Remove Services filter Services (8)
- Supply (3) Apply Supply filter
Contract information field: Method of procurement
- (-) Remove Negotiated Procedure filter Negotiated Procedure (8)
- Direct Agreement (24) Apply Direct Agreement filter
- Restricted Call for Tender (9) Apply Restricted Call for Tender filter
- Service contracts - International Restricted Procedure with prior publication (3) Apply Service contracts - International Restricted Procedure with prior publication filter
- Informal Consultation (2) Apply Informal Consultation filter
- Competitive Dialogue (1) Apply Competitive Dialogue filter
- Service contracts - Exceptional Negotiated Procedure with a single offer (1) Apply Service contracts - Exceptional Negotiated Procedure with a single offer filter
- Special Fund (Procurement Agent) (1) Apply Special Fund (Procurement Agent) filter
Countries:
Armenia
Programme:
INSC
Budget year:
2009
Amount:
€ 899.664,00
Countries:
Armenia
Programme:
INSC
Budget year:
2007
Amount:
€ 730.544,68
Countries:
Russia
Programme:
TACIS
Budget year:
2006
Amount:
€ 370.000,00
Countries:
Russia
Programme:
INSC
Budget year:
2007
Amount:
€ 1.469.819,16
Project Description
1 Introduction
Countries:
Armenia
Programme:
TACIS
Budget year:
2003
Amount:
€ 200.000,00
Full title of the project
Services required for detailed design studies aiming at defining the optimal solution for the qualification of the LBB concept of the primary circuit including the surge line at the Unit 2 of ANPP.
Countries:
Armenia
Programme:
TACIS
Budget year:
2006
Amount:
€ 1.564.293,56
The purpose of this contract is to:
Countries:
Armenia
Programme:
TACIS
Budget year:
2000
Amount:
€ 956.247,86
Introduction
Countries:
Armenia
Programme:
TACIS
Budget year:
2004
Amount:
€ 400.000,00
Full Project Title:
Services required for detailed design studies aiming at defining the optimal solution for the qualification of the LBB (Leak Before Break) concept of the primary circuit including the surge line at the Unit 2 of ANPP.