Procurement of spare parts for Zaporozhye NPP
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Search
Contract information field: Programme
Contract information field: Country
Contract information field: Budget year
- 2007 (1) Apply 2007 filter
- 2006 (5) Apply 2006 filter
- 2005 (2) Apply 2005 filter
- (-) Remove 2003 filter 2003 (18)
- 2002 (5) Apply 2002 filter
- 2001 (5) Apply 2001 filter
- 2000 (1) Apply 2000 filter
- 1999 (3) Apply 1999 filter
- 1998 (4) Apply 1998 filter
- 1997 (24) Apply 1997 filter
- 1996 (23) Apply 1996 filter
- 1995 (12) Apply 1995 filter
- 1994 (20) Apply 1994 filter
- (-) Remove 1993 filter 1993 (18)
- 1992 (28) Apply 1992 filter
Contract information field: Status
Contract information field: Contractor
- ENCO - Enconet (2) Apply ENCO - Enconet filter
- VHB Germany (2) Apply VHB Germany filter
- Ansaldo Energia (1) Apply Ansaldo Energia filter
- APC DISTRIBUTION LIMITED (1) Apply APC DISTRIBUTION LIMITED filter
- Bankomzvjazok (1) Apply Bankomzvjazok filter
- Bopp & Reuther (1) Apply Bopp & Reuther filter
- Burklin (1) Apply Burklin filter
- Canberra (1) Apply Canberra filter
- Deugro (1) Apply Deugro filter
- Iberdrola (1) Apply Iberdrola filter
- Limitorque (1) Apply Limitorque filter
- Lisega (1) Apply Lisega filter
- Persta (1) Apply Persta filter
- SEMPELL AG (1) Apply SEMPELL AG filter
- Siemens (1) Apply Siemens filter
- svt Brandschutz (1) Apply svt Brandschutz filter
Contract information field: Sector
Contract information field: Types of activities
Contract information field: Partner (Beneficiary)
- (-) Remove EnergoAtom filter EnergoAtom (18)
- (-) Remove State Scientific Center of Russian Federation "Institute of Theoretical and Experimental Physics" filter State Scientific Center of Russian Federation "Institute of Theoretical and Experimental Physics" (0)
- Rosenergoatom (23) Apply Rosenergoatom filter
- Rostechnadzor (7) Apply Rostechnadzor filter
- MINATOM RF, later ROSATOM (since 12/2007) (6) Apply MINATOM RF, later ROSATOM (since 12/2007) filter
- Nuclear Regulatory Administration (NRA) of Ukraine (3) Apply Nuclear Regulatory Administration (NRA) of Ukraine filter
- State Nuclear Regulatory Committee of Ukraine (SNRCU) (3) Apply State Nuclear Regulatory Committee of Ukraine (SNRCU) filter
- Armenian Nuclear Power Plant (2) Apply Armenian Nuclear Power Plant filter
- Chernobyl NPP (2) Apply Chernobyl NPP filter
- Emercom of Belarus (2) Apply Emercom of Belarus filter
- GOSKOMATOM (2) Apply GOSKOMATOM filter
- Ministry of Emergencies of Ukraine (2) Apply Ministry of Emergencies of Ukraine filter
- Administration of the Exclusion Zone SSE “Technocentre” (1) Apply Administration of the Exclusion Zone SSE “Technocentre” filter
- GAN (Ukraine) (1) Apply GAN (Ukraine) filter
- Ministry of Environmental Protection of Ukraine (1) Apply Ministry of Environmental Protection of Ukraine filter
Contract information field: Installation Types
Contract information field: Nuclear Power Plant
Contract information field: Nature
Contract information field: Method of procurement
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Beneficiary organisation: Energoatom, Ukraine
1) Background
As economical situation of Ukrainian NPPs was very difficult in the early 90’, there was an urgent need for spare parts in order to allow their operation.
Background
Project Background
Objectives
Background
Background
By 2004 the Tacis programme had been operating for 10 years and had already committed more than €1145 Million to improving nuclear safety in the former Soviet countries. Along with Russia, Ukraine was one of the biggest recipients of Tacis assistance.
Objectives
Project Description
Introduction